LUMUT HRSG
Project Name: Lumut Block 3 650MW Combined Cycle Power Plant
Location: Segari, Lumut, Perak, Malaysia
Mechanical & Electrical Erection Work – 3 units Heat Recovery Steam Generators, & Auxiliaries Equipment
Erection of HRSG Main Structures
Installation of Harps
Installation of Inlet Duct Wall Casing
Installation of HP and LP Steam Drums
Fit-up and welding of HRSG internal piping
Fit-up and welding of steam piping
Erection of HRSG Exhaust Stack
Erection of HRSG Exhaust Stack
Installation of Transmitters
Cabling work for HRSG Electrical system
Cabling Work for HRSG control valves
Insulation work for HRSG